Edwards Road Box Culvert Project

8/5/25 Trench excavated to several feet above subgrade (looking downstream)
8/5/25 Stream bypass dirtbag
8/6/25 Base stone looking downstream
8/7/25 Cote Crane set up on Davis Brook Rd side of culvert
8/7/25 Downstream toe wall set
8/7/25 Bottom Culvert Sections (facing Northwest)
8/7/25 Contractor placing the upstream toe wall (facing northwest)
8/7/2025 Contractor placing a bottom culvert section (facing west)
8/8/2025 Setting top half of clamshell starting at upstream end




















As of August 15th, Edwards Road has reopened. Thank you for your patience during the box culvert installation project and road closure.